How Long Should I Allow for a Complete New Roof Project?

The days on site are the part people ask about and rarely the part that decides when the roof is finished. Here is what to book, and in what order.

For an ordinary house in Flint a complete re-roof is a matter of days rather than weeks once the scaffold is up. That is the answer to the question people ask, and it is rarely the number that determines when the roof is actually finished.

This guide is the calendar rather than the programme: what to do, in what order, and which items are on the critical path.

Work Backwards From the Start Date, Not the Finish

The days on site are reasonably predictable. What is not, unless you plan it, is everything that has to happen before the first slate comes off — and those items run in parallel, so the longest one sets your start date.

Item One: The Heritage Check — Make It First

This costs nothing, takes minutes, and can change everything. Two questions for Flintshire County Council: is the address inside the Flint conservation area, and does any Article 4 direction apply to it?

For a like-for-like re-roof neither is likely to change anything, because putting the same covering back is not development at all. Where it matters is if you are changing the covering — and then it becomes the longest item on the whole calendar, because a permission is weeks rather than days.

Make this the first call, not the fourth. Discovering it after you have chosen a contractor and a covering costs weeks. Discovering it before you commission quotations costs one phone call.

Item Two: Survey and Quotations

Allow time to get three, and to compare them properly. A proper survey means the roof from outside and the roof space from inside, because the loft is where the condition of the underlay, the battens and the rafter ends is actually visible.

If the three are not quoting the same scope, the totals mean nothing — and establishing that takes a conversation with each of them rather than a glance at the bottom line.

Item Three: The Three Things That Run in Parallel

Materials

Stock coverings are generally quick. A specific slate, a particular tile, or anything being matched to existing work takes longer. Where reclaimed material is involved, availability rather than price is often the constraint — and on Flint's slate stock that comes up regularly.

Scaffolding

Subject to the scaffolder's diary, and where it has to stand on the public footway, subject to a licence. On the tighter terraced streets that is common, and the licence is frequently the longest lead item on a job that needs one.

Building control

Either a notification, or self-certification by a roofer registered under a competent person scheme. Agree which, and when, before the start date rather than after.

Item Four: On Site

PhaseWhat happensRelative length
ScaffoldErected a day or two before work startsShort
StripCovering, battens and underlay off, in sectionsShort and noisy
StructureInspection; timber repairs if neededUnpredictable
RebuildUnderlay, battens, covering, lead, ridge, vergesThe bulk of it
JunctionsChimneys, valleys, abutments, party lineSlow — and worth it
Ventilation and insulationEaves, ridge, thermal upgradeModerate
FinishGutters tested, site cleared, scaffold struckShort

On a slate roof the strip and rebuild both run longer than they would in interlocking tile, because a slated roof takes several times as many units per square metre. If the slates are being sorted for re-use, longer again — everything is handled twice.

Choosing When

Spring

Arguably the best window. Conditions improving, daylight lengthening, and demand has not yet peaked.

Summer

The obvious choice and therefore the busiest. Everyone books roofing for summer, so lead times are longest and you may wait months for a contractor worth waiting for.

Autumn

Perfectly workable and often good availability as the summer rush clears. The risk is that a job starting late can run into worse conditions if anything delays it, so it suits straightforward roofs better than complicated ones.

Winter

Entirely possible and frequently the shortest wait. Expect a longer programme for the same work, because of daylight and weather days. The one genuine caveat is mortar, which does not like frost — another reason mechanically fixed ridge and verge systems are the better specification anyway.

What Genuinely Extends It

  • A required permission — by far the largest
  • Slate rather than interlocking tile — far more units to lay
  • Sorting original slates for re-use — everything handled twice
  • Multiple chimneys and valleys — cutting and lead work
  • Defective timber found at the strip — unpredictable by definition
  • A footway scaffold licence — affects the start date, not the work
  • Material lead times on anything non-standard
  • Winter daylight, and sustained wind or driving rain

Why a Shorter Programme Is Not a Better One

A quoted duration noticeably shorter than everyone else's is worth questioning rather than welcoming. The steps dropped to hit a fast date are the invisible ones: a proper structural inspection, correctly lapped underlay dressed into the gutter, lead formed and dressed into the brickwork rather than bedded in mastic, ventilation details at the eaves.

You will live with this roof for decades. Two extra days on site is not the variable worth optimising.

The Regulations in Wales, in Brief

Flint is in Wales, and the position is not the same as it is across the border. Planning: section 55 of the Town and Country Planning Act 1990 applies in Wales as well as England, so a like-for-like re-roof is not development at all and needs no permission. But Wales never adopted the 2015 permitted development order that applies in England — it still uses the General Permitted Development Order 1995, as amended.

Building regulations: regulation 23 of the Building Regulations 2010 applies in England and Wales alike. Where more than 50% of the roof's surface area is renewed, or the work forms part of a major renovation, the roof must be brought up to current thermal standards so far as that is technically, functionally and economically feasible. A patch repair does not trigger it, and neither does a roof over unheated space such as a detached garage.

Where Wales differs is the guidance. Wales has its own Approved Document L — the 2022 edition for use in Wales, incorporating the 2024 amendments — and its figures are not England's. For a new or replacement roof element in an existing dwelling Wales sets 0.13 W/(m²K) against England's 0.15, so the Welsh standard is the tighter of the two. Confirm the figure that applies to your project with Flintshire's building control team before the work is priced. The full position is on our Flint page.

Want a Realistic Calendar?

We will tell you what has to happen before we start and roughly how long each part takes.

More New Roof Advice for Flint

New roof installations in Flint →
All new roof guides →
New Roof Installations Chester →

Questions

Quick Answers

How far ahead should I start?
If the roof needs doing and it is not an emergency, start the conversation several months before you want the work done. The items that set the start date — material lead times, the scaffolder's diary, any permission — all run in parallel and the longest one wins.
What sets the start date rather than the finish date?
Usually a scaffold licence where one is needed, or a material lead time on anything being matched. Where a permission is required for a change of covering, that is the longest single item by a wide margin.
Can roofing be done in winter?
Yes. The constraints are wind, driving rain, ice on the scaffold and daylight hours rather than cold itself. Expect a somewhat longer programme for the same work, and expect more flexibility to be needed on dates.
Is summer the best time to book?
Not necessarily. Summer is when everyone books, so lead times are longest and you may wait months. Late winter and early spring often have much better availability and perfectly workable conditions.
Areas We Cover

New Roof Installations in Flint and Across the Area

Complete new roofs, re-roofing and roof replacement across Chester, the Wirral, Deeside and the surrounding areas.

Free Quotation

Ask About Timings in Flint