It can, it usually should, and it should almost always happen early. There is also a regulatory threshold on larger projects that is worth knowing before the programme is set.
Yes — and if a roof is going to need replacing within a few years, a renovation is unambiguously the moment. The technical side is straightforward. What determines whether it goes well is sequencing, and one regulatory threshold that catches people out on larger projects.
Everything that follows is vulnerable to water from above — plaster, decoration, flooring, joinery, electrics. Roofing is also the trade most exposed to weather, so it needs somewhere in the programme to absorb a bad fortnight.
Putting the roof first removes the largest single risk to everything downstream. Putting it last means a wet spell delays the completion of the whole project rather than one phase of it, and a roof that lets go mid-programme ruins finished work.
There is a second reason, and it is the one people appreciate afterwards. The strip is the only opportunity anyone will have to see the roof structure. If rafters, purlins or wall plates need attention, that is far better discovered before internal finishes go up than after.
This is the largest avoidable cost on a domestic renovation, and it is avoidable purely by sequencing.
A scaffold erected for the roof can also serve:
For an ordinary re-roof the position is straightforward: where more than 50% of the roof's surface area is renewed, the roof has to be brought up to current thermal standards so far as that is technically, functionally and economically feasible.
On a whole-house renovation there is a second threshold. Work to more than a quarter of the surface area of the whole building envelope — walls, roof, floors, windows and doors together, not just the roof — counts as a major renovation, and that brings wider consequential requirements into play.
On a project doing the roof, replacing the windows, re-rendering and insulating walls, that quarter of the total envelope is easy to cross without anyone noticing. It is a conversation to have with building control at the design stage, not once the work is running.
This changes more than people expect.
If you have bought a property to renovate and can do the roof before moving in, take the option. It is materially easier and usually faster.
The house stays weathertight either way. Roofs are stripped in sections, not all at once, and open areas are sheeted at the end of each day and when weather requires.
The roof is the part of a renovation with the largest genuine unknown, and it is unknown to everybody equally — no contractor can see through a covering.
The professional way to handle it is not to hope:
The principle is simple: everything needing access from outside happens in one scaffold period, and nothing internal and vulnerable starts until the building is weathertight above it.
Deeside is in Wales, and the position is not the same as it is across the border. Planning: section 55 of the Town and Country Planning Act 1990 applies in Wales as well as England, so a like-for-like re-roof is not development at all and needs no permission. But Wales never adopted the 2015 permitted development order that applies in England — it still uses the General Permitted Development Order 1995, as amended.
Building regulations: regulation 23 of the Building Regulations 2010 applies in England and Wales alike. Where more than 50% of the roof's surface area is renewed, or the work forms part of a major renovation, the roof must be brought up to current thermal standards so far as that is technically, functionally and economically feasible. A patch repair does not trigger it, and neither does a roof over unheated space such as a detached garage.
Talk to us at the design stage rather than the scheduling stage. Where the roof sits affects every trade behind it.
New roof installations in Deeside →
All new roof guides →
New Roof Installations Chester →
Complete new roofs, re-roofing and roof replacement across Chester, the Wirral, Deeside and the surrounding areas.
Tell us about the property and the roof in Deeside, and we will come back to you — usually the same day.
Prefer to talk? Call 07464 259566 · WhatsApp 0044 7464 259566 · Email Evensbuddy@yahoo.com