How Long Does a New Roof Installation Take?

The days on site are usually the shortest part. What determines when your roof is actually finished is mostly what happens before anybody climbs a ladder.

For an ordinary house, a complete re-roof is a matter of days rather than weeks on site once the scaffold is up — longer on a complex roof, longer again if something turns up in the timbers.

That is the easy part of the answer. The more useful question is when to book it, because the gap between deciding you need a roof and having one is usually dominated by everything that happens before the first tile comes off.

Stage One: Survey and Quotation

Quick, and it should not be rushed. A proper survey means the roof from outside and the roof space from inside, because the loft is where the condition of the underlay, the battens and the rafter ends is actually visible.

Allow time to get three quotations and to compare them properly. If they are not quoting the same scope, the totals mean nothing — and establishing that takes a conversation with each of them.

Stage Two: The Heritage Check

Two free enquiries, and they belong before the quotations rather than after: is the address inside a conservation area, and is the building listed?

For a like-for-like renewal neither is likely to change anything — putting the same covering back is not development at all. Where it matters is if you are changing the covering, because inside a conservation area that test is applied more tightly and an application can be weeks rather than days. It is also the item most likely to change what you can have, so it should be settled before anything is ordered.

Make this the first phone call, not the fourth. Establishing the heritage position costs nothing and takes minutes. Discovering it after you have chosen a contractor and a covering costs weeks.

Stage Three: Ordering and Booking

Three things run in parallel here, and the longest of them sets the start date.

Materials

Stock coverings are generally quick. A specific slate, a particular clay tile, or anything being matched to existing work can take considerably longer. Where reclaimed material is involved, availability rather than price is often the constraint.

Scaffolding

Subject to the scaffolder's diary, and where the scaffold has to stand on the public footway, subject to a licence from the council. That licence is frequently the longest lead item on a job that needs one, so it gets applied for early.

Building control

Either a notification, or self-certification by a roofer registered under a competent person scheme. Agree which, and when, before the start date rather than after.

Stage Four: On Site

PhaseWhat happensRelative length
ScaffoldErected a day or two before work startsShort
StripCovering, battens and underlay off, in sectionsShort and noisy
StructureInspection; timber repairs if neededUnpredictable
RebuildUnderlay, battens, covering, lead, ridge, vergesThe bulk of it
JunctionsChimneys, valleys, abutmentsSlow — and worth it
Ventilation and insulationEaves, ridge, thermal upgradeModerate
FinishGutters tested, site cleared, scaffold struckShort

The rebuild dominates, and its length is driven mainly by the covering. Interlocking tiles go on considerably faster than slates or plain tiles, because each unit covers more area — a slated roof takes several times as many pieces per square metre, each lifted, positioned and nailed by hand.

What Weather Actually Does

Worth being precise, because “bad weather” covers several different problems with different consequences.

  • Wind is the real constraint and the one people least expect. Handling large coverings and sheet material at height in wind is dangerous, and it is a safety decision rather than a comfort one.
  • Driving rain stops work for safety and for quality — laying underlay and battens in the wet is not good practice.
  • Cold is much less of a problem than people assume. The exception is anything involving mortar, which does not like frost.
  • Daylight is the quiet winter constraint. A December working day is a great deal shorter than a June one.
What weather does not do is put water in your house. A roof is stripped in sections, never all at once, and any open area is sheeted at the end of each day and whenever weather is coming. Rain extends the programme; it does not expose the building.

What Genuinely Extends It

  • A required planning application — by far the largest
  • Slate or plain tile rather than interlocking tile — far more units to lay
  • Sorting original slates for re-use — everything handled twice
  • Hips, valleys, dormers and multiple chimneys — cutting and lead
  • Defective timber found at the strip — unpredictable by definition
  • A footway scaffold licence — affects the start date, not the work
  • Material lead times on anything non-standard
  • Winter daylight, and sustained wind or driving rain

Living With It

  • You stay in the house, and it stays weathertight throughout
  • The strip is genuinely noisy — and it is the shortest phase
  • Decades of dust come out of the loft. Bag or move anything stored there first
  • Scaffolding affects privacy and light for the duration
  • Parking and access change — skip, materials, scaffold
  • Tell the neighbours, with a rough end date, particularly on attached property

Why a Shorter Programme Is Not a Better One

A quoted duration noticeably shorter than everyone else's is worth questioning rather than welcoming. The steps dropped to hit a fast date are the invisible ones: a proper structural inspection, correctly lapped underlay dressed into the gutter, lead formed and dressed into the brickwork rather than bedded in mastic, ventilation details at the eaves.

You will live with this roof for decades. Two extra days on site is not the variable worth optimising.

The Regulations, in Brief

Two systems, and they are separate. Planning: a like-for-like re-roof does not materially affect the external appearance of a building, so under section 55 of the Town and Country Planning Act 1990 it is not development at all and needs no permission. A visible change of covering can be a different matter, particularly inside a conservation area.

Building regulations: where more than 50% of the roof's surface area is renewed, or the work forms part of a major renovation, regulation 23 of the Building Regulations 2010 requires the roof to be brought up to current thermal standards so far as that is technically, functionally and economically feasible. A patch repair does not trigger it, and neither does a roof over unheated space such as a detached garage. The work is signed off through building control or by a roofer registered under a competent person scheme, and you should receive a certificate.

The full position — conservation areas, Article 4, the U-value figures and the certification routes — is set out on our New Roof Installations Chester page. If your property is in Wales, see Flint or Deeside instead — Wales has its own Approved Document L with different figures, and still uses the 1995 permitted development order rather than the 2015 one.

Want a Realistic Timeframe?

We will tell you what has to happen before we start and roughly how long each part takes.

More New Roof Guides

All new roof guides →
New Roof Installations Chester →

Questions

Quick Answers

What usually takes the longest?
Not the roofing. Where a planning application is needed it is the longest single item by a wide margin. Where none is needed, it is usually the scaffold licence or the material lead time.
Can a roof be replaced in winter?
Yes, and it routinely is. The constraints are wind, driving rain, ice on the scaffold and daylight hours — not cold itself. Expect a somewhat longer programme for the same work.
Is summer the best time to book?
Not necessarily. Summer is when everyone books, so lead times are longest. Late winter and early spring often have better availability and perfectly workable conditions.
What happens if it rains during the job?
Work stops if conditions are unsafe or would compromise quality, and any open area is sheeted. The roof is stripped in sections precisely so the building is never left open, so rain delays the programme rather than putting water in the house.
Areas We Cover

New Roof Installation Areas We Cover

Complete new roofs, re-roofing and roof replacement across Chester, the Wirral, Deeside and the surrounding areas.

Free Quotation

Ask About Timings

Tell us about the property and the roof, and we will come back to you — usually the same day.

Prefer to talk? Call 07464 259566 · WhatsApp 0044 7464 259566 · Email Evensbuddy@yahoo.com